Friday, October 5, 2007
working on the 'rubbing' part of the Texas Rail.
This is an all day process for four people to hand
rub the day old concrete to remove the bubbles
and imperfections for a 33' section.
We still have to keep the rail wet during the
rubbing process. One guy spends the day moving
around burlap and keeping the uncovered portions wet.
The rest of the crew continues to form the
upcoming rail segments. The roadway crew is
still working of sidewalk prepartion and granite
curbing.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment