Friday, November 30, 2007


Finishing up removing the temporary abutment.

Finishing the Prince Street slopes and resetting
the street light.

Thursday, November 29, 2007


Removing the steel sheeting that made up the
temporary abutment for the detour.

Tuesday, November 27, 2007


Sammis retaining wall.

Tuesday, November 20, 2007


Winter Arrived today. No Work.

Monday, November 19, 2007


Adding Stone Fill to the Prince Street slopes.

Concrete for the retaining wall placed today.

Friday, November 16, 2007


Adding the front face form with a stone pattern
form liner so that the concrete looks like a stone wall.

Added some more drainage to prince street.

Wednesday, November 14, 2007


Winterset continues to excavate the inner part of
Prince Street. Drainage from main street will
discharge into this settling area inside the curve
of the road. From there an outlet pipe will drain the
water the rest of the way to the river.

Forming the retaining wall that will be along
the side of the driveway that we had to raise
along with raising the north end of the bridge.

Friday, November 9, 2007

Remove the Maybe bridge


Area prepared to roll the bridge onto.

Rolling the bridge onto to the dismantling area.

Dismantling the Maybe bridge into pieces.

Tuesday, November 6, 2007


Winterset continues to remove the detour.

Friday, November 2, 2007


Building a retaining wall for the side of the driveway
that is across from Cumberland Farms.

Thursday, November 1, 2007


Rebuilding Prince Street