Thursday, August 30, 2007


Working on the 12" waterline in the South end of the bridge.

This is the special connection for the 12" waterline from the roadway to the bridge.
They are nearly finished with installing the waterline on the bridge.
Now that the concrete for abutment two is complete up to almost the roadway level, we will be able to backfill the area with gravel and finish much of the stone fill around the abutment. The bridge decking will begin soon. Possibly poured on Sept. 17th. They will start putting down the Stay in Place decking on Friday.