Debris from the remenents of the 1925 bridge make installing the cofferdam sheets a slow process.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhx2Zf7hvqCVJIBPPo4YSG20FxdgrlA0g8HzcDP615gM00AAlXfUR_15dWvjiqUFtNObIixO6mfBiCWPGNhmRPJyNzp0oF4cRNRoezKoMAmafNxhsZ_S-7GgJ6uftzadLkWmf-gee62kYk/s400/Pier+1024+Cofferdam+24.jpg)
Through a change in design, they change from drilled shaft to spread footing for the pier.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhwZubCdyW01kSOWuRv3GzumyB9hNPk_HBKCJhvvgLXz0wYbJfQ5cC7ZSx5biXJqIt4uyuFoPZ8YJo8lxlaRxui-PQIleun8r2y7g3yCXXs4qklmPJW5TxVTU6ir7roOgacVKtnhf7yEyM/s400/Soldier+Pile+Retaining+wall+11.JPG)
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEga0ss36uKl6ga_FsyBR4KHCu7Ta_91Ljbu9yXIddi6Qa4LwZUWsJwIG43xO4I9ZY8RLFLYeMWDGig-jJEQn-DWggOQZW04z1jAcdT4JD4c3Tpbgv-6K9cw73Q382twSJ6bH2LHs1IaaL0/s400/Soldier+Pile+Retaining+wall+10.JPG)
But they continue to work on the project anyway. They build the timber retaining wall
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgzY7XZ8DXx_A98BaKs5A7YW9xX7lUQlJ4eHCfhN8YW3dFA-5yDJoEd945vqBgB4CyGQdvEcEChuuwiK8-flM8RKfDgJ3V8hIihT11tKafewf2jETTk61ZTj8XlTI6kz6GUGeGR8kMrDrU/s400/progress+06a.jpg)
Winterset is unsucessfull in their attempt to open the detour before the paving plants shut down for the winter.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEh2y2kQMSDdCd7_L_95ME3JX9xU8HCtIRNGB0SbKW2SHmnNQvitD_FFrdeMlV6mZWiGcmrb8b96yUnDPxOggc4wev26jPqMLkoPAFekWux4b2H0Te1PGLxOrIRlzX4WQ1MtPCHpBudrpu8/s400/Detour+Construction_0669+Maybe+Launch+10.jpg)
Contractor spends the fall building the temporary detour.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgZ717RPiziTnM6d1wKX-Q9LoBNNrfLOELUBfBsu9uz6Mp2lVldDORMiNiTzfhDdSWeLZMKzZmhsjLsphUb1KgWc1O6bIxiKw1yQSMWqfJccvqdW4mkzyARCmF9QwusSA4diH5kGMafeyU/s400/Clearing+B.JPG)
Winterset is the low bidder. Clearing begins
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEj5xh7yJjU1HYOOpExTMV69i-qJGFLsLH_JfMh7Uvgjlq52ppUhXg12EAn_VGtAF3GKUr6yTKj-0Fq0uW2at-iEW1rX1JnrvTghxR2jnJeyRgF3hkwTvyKptDCMNq-xLf8GWvY3uRw6s6w/s400/Progress+01.JPG)
Contract letting date set for new main street bridge 09/29/06