Abutment Two was poured up to within 8' of the Bottom of the steel beams this week. About 150 cy of concrete.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjgVbdveFmJYJJxky4lFOgPGNEt_DIChRZtQqbfX83PnTJvbhKlIO-OlYPrhgwvSOxhAXTgKn3gpZUQfweQvQRUfR7LZmBcRIHVEzr1K1XjkLa33rpl8OT_CWw18BxkHt6IdOuHAl2hyDQ/s400/102_1301.JPG)
Winterset worked on Subbase of crushed stone, the roadway base for Prince Street down on the lower end. They used the excavated material from the roadway to build a crane pad for unloading the steel beams that will arrive in the third week of August.