Abutment Two was poured up to within 8' of the Bottom of the steel beams this week. About 150 cy of concrete.
Friday, July 27, 2007
Monday, July 23, 2007
Friday, July 20, 2007
Monday, July 16, 2007
Working on Abutment 2 Footing. L Bars are #11's and weigh 138 pounds so they have to be individually set by crane. We should be ready for concrete on Wednesday morning.
Adding waste material to the slope on Prince Street getting ready to add stone fill to the slope.
We've started installing the drainage at abutment 1.
Adding waste material to the slope on Prince Street getting ready to add stone fill to the slope.
Thursday, July 12, 2007
Over 6" Rain in Randolph
Light rain in the morning didn't bother, but the heavy rain that started about 1:00 ended work for the day. Over 6" of rain in flooded us out. The erosion control bituminous curb we installed on the north end helped contain much of the runoff in the abutment two area.
The pavement on the road on the south end of the bridge has deep ruts, so a lot of water ran by the drop inlets (drains) and eroded the gravel backfill along the west side of abutment one.