Friday, December 21, 2007


Winterset has shut down operations for the winter.
On a side note: The Ice Skating rink has opened.

Friday, December 14, 2007


Winterset has spent this week loading out materials
and equipment to shut down the operations
until next April. The crane in the photo has
had it's weights removed, and the tracks moved in
in prepartion of being hauled out soon.

Monday, December 10, 2007


Guardrail on Prince Street.

Thursday, December 6, 2007


Installing guardrail on Prince Street.



Removing the temporary detour abutment

Monday, December 3, 2007


10" to 12" Snow on Monday. No work.

Friday, November 30, 2007


Finishing up removing the temporary abutment.

Finishing the Prince Street slopes and resetting
the street light.

Thursday, November 29, 2007


Removing the steel sheeting that made up the
temporary abutment for the detour.

Tuesday, November 27, 2007


Sammis retaining wall.

Tuesday, November 20, 2007


Winter Arrived today. No Work.

Monday, November 19, 2007


Adding Stone Fill to the Prince Street slopes.

Concrete for the retaining wall placed today.

Friday, November 16, 2007


Adding the front face form with a stone pattern
form liner so that the concrete looks like a stone wall.

Added some more drainage to prince street.

Wednesday, November 14, 2007


Winterset continues to excavate the inner part of
Prince Street. Drainage from main street will
discharge into this settling area inside the curve
of the road. From there an outlet pipe will drain the
water the rest of the way to the river.

Forming the retaining wall that will be along
the side of the driveway that we had to raise
along with raising the north end of the bridge.

Friday, November 9, 2007

Remove the Maybe bridge


Area prepared to roll the bridge onto.

Rolling the bridge onto to the dismantling area.

Dismantling the Maybe bridge into pieces.

Tuesday, November 6, 2007


Winterset continues to remove the detour.

Friday, November 2, 2007


Building a retaining wall for the side of the driveway
that is across from Cumberland Farms.

Thursday, November 1, 2007


Rebuilding Prince Street

Monday, October 29, 2007


Removing the detour is the next thing to do.

Thursday, October 25, 2007


Paving the second to last layer of pavement is complete,
and the bridge is open.

We will now be working on removing the temporary
bridge and rebuilding Prince Street.

Wednesday, October 24, 2007


The first of two lifts of pavement is being paved
today. The top lift will be paved next June.

Monday, October 22, 2007


This machine is called a cold planer. It's here to
plane the hotmix surface in the areas where the
old hotmix meets the new to create a smooth
transition.

Installing the membrane on the deck of the bridge.
The membrane is a sheet of waterproof material that
looks a lot like asphalt roof shingle. The machine
heats the asphalt material and melts the sheet to
the deck. The surface is a stone type grit to protect
asphalt material until it gets paved (Wednesday).

There is a lot going on today.
Winterset working on the final segment of Texas Rail on the abutement.
Winterset working on Cumberland Farms driveway.
Gendron working on Cumberland Farms curb and sidewalk.
AD Rossi installing the deck membrane.

Thursday, October 18, 2007


Installing some of the project drainage system
on the south end of the project.

Tuesday, October 16, 2007


Three of the six lights were installed today.

Working on landscaping the Cumberland Farms
sidewalk area.