Removing the detour is the next thing to do.
Monday, October 29, 2007
Thursday, October 25, 2007
Monday, October 22, 2007
Installing the membrane on the deck of the bridge.
The membrane is a sheet of waterproof material that
looks a lot like asphalt roof shingle. The machine
heats the asphalt material and melts the sheet to
the deck. The surface is a stone type grit to protect
asphalt material until it gets paved (Wednesday).
Tuesday, October 16, 2007
Monday, October 15, 2007
Wednesday, October 10, 2007
Tuesday, October 9, 2007
Friday, October 5, 2007
working on the 'rubbing' part of the Texas Rail.
This is an all day process for four people to hand
rub the day old concrete to remove the bubbles
and imperfections for a 33' section.
We still have to keep the rail wet during the
rubbing process. One guy spends the day moving
around burlap and keeping the uncovered portions wet.
The rest of the crew continues to form the
upcoming rail segments. The roadway crew is
still working of sidewalk prepartion and granite
curbing.
Thursday, October 4, 2007
Wednesday, October 3, 2007
Tuesday, October 2, 2007