Friday, September 28, 2007
Today we finished the concrete for the sidewalks
across the bridge.
Working on adding dense graded crushed stone
to the subbase on the south end of the bridge.
Traffic was so heavy today that we didn't get
all of it done in preparation for the paving crew
to cover it on Monday. It's amazing how many
people are out and driving around in the middle
of a weekday in this town.
Thursday, September 27, 2007
Wednesday, September 26, 2007
Now that the roadway is higher and the waterline
installed, they then could put the stormwater
drainage system over it. Maintaining traffic with
this work is very difficult and we hear of big delays.
We have no choice but to run one way traffic through
the project for part of the day.
We Placed a small part of the concrete sidewalk.
Tuesday, September 25, 2007
Monday, September 24, 2007
Today we poured the concrete for approach slab 2 and made
the final connection for the fiber optic conduits. But the biggest
part of the day was to remove the old pavement and build the roadway
up higher with crushed stone. The amount of traffic in
Randolph in the middle of a Monday is incredible. Traffic must be stopped
in one lane while we work on the other, and this backs traffic up big time.
We hope to have it all ready for paving by next Monday.
part of the day was to remove the old pavement and build the roadway
up higher with crushed stone. The amount of traffic in
Randolph in the middle of a Monday is incredible. Traffic must be stopped
in one lane while we work on the other, and this backs traffic up big time.
We hope to have it all ready for paving by next Monday.
Friday, September 21, 2007
Wednesday, September 19, 2007
Monday, September 17, 2007
Friday, September 14, 2007
Deck reinforcing steel is nearly complete. The Yellow machine in the middle of the bridge is called a screed machine. The concrete will be pumped onto the deck, and the screed machine will smooth the concrete out to a uniform 9" thick layer. We will start Monday morning and the 250 cy will be placed in about 5 hours.
Tuesday, September 11, 2007
Saturday, September 8, 2007
Friday, September 7, 2007
The Stay-in-Place forms are now complete.
Forming the outside portion of the deck with wood forms that will be removed after the deck is cured.
On a side note, I have had a lot of comments about the steel girders being rusty. The weathering process (rust) that occurs after installation eventually decreases and from that point on the finish acts as a protective coating for the base metal. This steel never completely stops rusting. It develops an oxide on its surface that essentially stops corrosion.
Funny....rust that stops rust.
On a side note, I have had a lot of comments about the steel girders being rusty. The weathering process (rust) that occurs after installation eventually decreases and from that point on the finish acts as a protective coating for the base metal. This steel never completely stops rusting. It develops an oxide on its surface that essentially stops corrosion.
Funny....rust that stops rust.
Thursday, September 6, 2007
Tuesday, September 4, 2007
Subscribe to:
Posts (Atom)