Tuesday, October 14, 2008


The lines were installed today. The project is now Complete

Tuesday, September 23, 2008


Because the bridge will expand and contract
due to temperature changes, a joint must be installed
so that there will not be a large crack in the pavement
on each end of the bridge. The type of joint for this
bridge is called a Asphaltic Plug Joint.
First 18" of pavement is removed over the end of the
bridge at each abutment. A steel plate is placed over
joint, and then a rubber type material is hot poured
in the joint and ¾" aggregate is mixed in the hot
rubber. This allows a very smooth riding joint that is
also very durable.



Tuesday, July 29, 2008


Paving to top lift of Bituminous concrete Pavement.
The lift thickness is 1 ½" thick.

Monday, July 28, 2008


Paving New England Land Company's Parking lot.

Friday, July 25, 2008


Pike brought in a grinding machine (cold planer)
to grind the begin edge for paving.
We will be paving Monday and Tuesday July 28 & 29

Wednesday, July 23, 2008


Working on grading and added concrete curbing
for the New England Land Company parking lot.

Tuesday, July 15, 2008


Staging area cleaned up and a stone ditch added
to the edge of prince street.

Friday, July 11, 2008


The last of the concrete sidewalk being placed
on the north end of the bridge.

Wednesday, July 9, 2008


Installing granite curbing and sign bases for
the Vt 12A Island.

Pouring concrete for sidewalk and adding final
touches to the Vt12A Island.

Thursday, June 26, 2008


Paving the first of two layers of Pavement
on Prince Street.

Friday, June 20, 2008


Stone retaining wall re-stacked. Hand rail added.

Monday, June 16, 2008


Photo of retaining wall in late 2006.

Dismantled the stone retaining wall that was in
front of the house just west of the Fire Station.
The two 24" maple trees that had to be
removed when the power lines were re-routed.
Winterset removed the stumps, and in this photo
you can see the sleeves for the concrete which
will hold a new hand rail. The steps will not be redone.

Tuesday, June 3, 2008


Plans called for raising the Sewer Manhole cover
on Prince Street that was supposed to be in the new
roadway just west of the bridge (almost under the bridge).
It wasn't there. We spent two days with the town running
camera's up from the next manhole. It was very hard to
locate. We finally found it.
It had been buried years ago in about 10' of embankment.
And because it was further north than it was supposed to be,
we had broken part of the pipe right next to the manhole.
We were very lucky last summer when driving the steel
sheets to the temporary detour abutment. We came close
enough to break the pipe, but not plug it.
In the end, it cost us three days of work and instead of just
raising the lid, we had to build a new manhole from the
base up.

Friday, May 23, 2008


Finished the side slopes on the Northwest corner
of the bridge. Brought the driveway that goes down
behind New England Land Company Driveway up
to it's final grade.

Monday, May 19, 2008


Working on the side slope of Price Street.
Adding Stone Fill over Geotextile fabric.

Thursday, May 1, 2008


The Winterset work crew working on the Solid waste bridge over I-91 in Hartford could not work on that project during the last week in April. They returned to Randolph and spent this week working on the stone fill slope on the upstream - north side of the bridge.

Friday, April 25, 2008

Winterset worked the winter on projects in Bristol New Hampshire and the bridge across the Connecticut River in Haverhill NH. They resumed construction of the bridge over the I-91 in Hartford this spring also.
There has not been any activity on this project since December. The project wintered well with no apparent problems. The concrete rail has many small cracks that are typical with this type of rail. In fact, even though there are many cracks, there are less cracks than other projects have had using this same design. Maybe the use of AA concrete aggregate with HP-B concrete has helped to reduce the cracking??

Thursday, February 7, 2008

Winter



Snow is clogging the temporary intersection at
the junction of 12 and 12A. We will have to
work on snow removal.

Winterset has not been on site since mid December.
They have active projects in Bristol NH and Haverhill NH.

Friday, December 21, 2007


Winterset has shut down operations for the winter.
On a side note: The Ice Skating rink has opened.

Friday, December 14, 2007


Winterset has spent this week loading out materials
and equipment to shut down the operations
until next April. The crane in the photo has
had it's weights removed, and the tracks moved in
in prepartion of being hauled out soon.

Monday, December 10, 2007


Guardrail on Prince Street.

Thursday, December 6, 2007


Installing guardrail on Prince Street.



Removing the temporary detour abutment

Monday, December 3, 2007


10" to 12" Snow on Monday. No work.

Friday, November 30, 2007


Finishing up removing the temporary abutment.

Finishing the Prince Street slopes and resetting
the street light.

Thursday, November 29, 2007


Removing the steel sheeting that made up the
temporary abutment for the detour.